SCAFFOLDING SYSTEMS
Skyway scaffolding systems provide safe, efficient access in virtually any industrial or commercial application. Our product offering is comprehensive, and includes a complete range of components that allows us to tailor systems to meet the requirements of any job. Most importantly, Skyway has the expertise and experience to develop the right solution for every project. All our scaffolding products meet or exceed Canadian safety standards, and our rigorous ISO 9001-2000 quality program ensures our systems are maintained to exacting standards. Skyway scaffold systems maximize efficiency and safety – cost effectively.
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
New Winnipeg Airport YWG, EllisDon Construction • Materials and labour for departure ramp and road • Peak labour: 52 carpenters
• 20 tractor trailer loads of High Strength Light Weight aluminium shoring • Challenges – small laydown yard, tight work schedules
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water’s edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water’s edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water’s edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water’s edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water's edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water's edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006
Encana Foster Creek, AB. • Typical Skyway Oil Sands Project • 110 Men • 2.8MM in Equipment
• Construction, maintenance and shutdowns • On site since 2005
Encana Foster Creek, AB. • Typical Skyway Oil Sands Project • 110 Men • 2.8MM in Equipment
• Construction, maintenance and shutdowns • On site since 2005
Encana Foster Creek, AB. • Typical Skyway Oil Sands Project • 110 Men • 2.8MM in Equipment
• Construction, maintenance and shutdowns • On site since 2005
Encana Foster Creek, AB. • Typical Skyway Oil Sands Project • 110 Men • 2.8MM in Equipment
• Construction, maintenance and shutdowns • On site since 2005
Lions Gate Bridge, Vancouver BC • System Scaffold structure and containment for blasting & painting of Bridge steel • Total Scaffold height was over 300 ft. above Vancouver harbour waters
• Tower shown was at water's edge in North Vancouver • Other tower on pier surrounded by water just offshore of Stanley Park’s
famous seawall • Aluminum Truss & Shoring supported platform provided protection above sidewalks,
bicycle paths & traffic lanes at all times • Project started Fall 2004 & finished Summer 2006